10.11.2007

In the market for a fixer-upper, you say?

WASHINGTON — The latest problem with the trouble-plagued new U.S. embassy complex in Iraq is that the sprinkler systems meant to contain a fire do not work, according to officials in Congress and the State Department.

The previously undisclosed problem in the $592 million project was discovered several weeks ago when the fire-safety systems were tested and pipe joints burst, State Department representatives recently informed Congress.

The embassy complex, being built by First Kuwaiti General Trade and Contracting Co., has been marred by repeated problems. In May, when kitchen facilities at a guard camp that is part of the embassy complex were tested, the electrical system malfunctioned and wires melted. A subsequent inquiry showed that First Kuwaiti had used counterfeit electrical wiring that did not meet specifications, according to testimony at a congressional hearing in July.

(McClatchy)
According to State Department spokesman Sean McCormack, "Obviously, with any large complex construction project, especially one that is happening in a difficult security environment, there is the possibility that the schedule will slide to the right."

So, see? You just have to shove it back to the left a little and you can move right in.